Sand Reclamation
Melaka
29 June 2018
28 June 2019
Benalec Holdings Bhd

Sand reclamation for the purposes of Benalec Holdings Bhd’s contracts for a Proposed construction, completion and maintenance of rock revetment and associated works for Phase 2A, Phase 3A and Phase 3B (275 acres) between Kuala Sungai Melaka and Kuala Sungai Seri Melaka for Oriental Boon Siew Sdn Bhd and; Proposed reclamation works for 100 acres at Perairan Kota Laksamana, Kawasan Bandar 6, Daerah Melaka Tengah for Puncak Jasasia Sdn Bhd.

Project
Location
Commenced
End
Client

Description

Sand Reclamation
Melaka
12 July 2018
11 July 2019
Samudera Wibawa Sdn Bhd

Sand reclamation for the purposes of Samudera Wibawa Sdn Bhd’s contract for a Proposed 120 acres (48.57 ha) coastal reclamation and 50 acres (20.24 ha) of water chalets (without reclamation) at Pekan Klebang Seksyen III, Mukim Klebang Besar, Daerah Melaka Tengah, Melaka.

Project
Location
Commenced
End
Client

Description

Sea Sand Stockpile
Melaka
13 August 2018
12 August 2019
Sovereign CR ERYuan Sdn Bhd

Sea sand stockpile for the purpose of sales-on-demand for the local entrepreneurs/industry in the state of Melaka.

COMPLETED PROJECTS

Project
Location
Commenced
Ended
Contract Value

Description

Private Jetty – Phase 1
Tok Bali, Kelantan
2010
2014
RM70 Million

Construction & Completion work for the following :

  • Warehouse 60,000 sq ft
  • 10 Storage Tanks with a capacity of 200,000 litres per tank
  • Jetty 500 meters

Project
Location
Commenced
Ended

Description

Sand Reclamation
Pulau Melaka East 1
2013
2015

Delivery of sea sand to Pulau Melaka East 1, including selection and mobilisation of suitable equipment for the dredging, extraction, transporting and unloading of sea sand from the concession site.

The provisional quantity of the sea sand was 1,000,000 m³. We were also requested to monitor all operations and maintenance of the equipment, plants, machineries and vessels including all associated diesel/petrol and oil lubricants.

Project
Location
Commenced
Ended

Description

Diving Inspection
Kuantan Port
2014
2017

The project required us to design and supervise the construction of a breakwater, capital dredging and other ancillary works for the new Deep Water Terminal at Kuantan Port, Pahang for the East Coast Economic Region Development Council (ECER).

The scope of work for Kuantan Port consists of carrying out diving project for the inspection of underwater construction for the breakwater by the contractor at the Project Site as follows:

  • Breakwater base dredging and sand filling
  • Geotextile
  • Underlayer, toe and apron
  • Primary armour ACCROPODE II units